Week 5 - October 6 - 12
Pictures from Tuesday morning

Drywall has shown up. There is a stack in every room in the house. Here is some for the garage.

A stack for the living room. From the start of dry-walling it's about 30 to 45 days until closing!
On Tuesday morning we had it inspected by an inspector we hired. The few minor things that he noted were passed along to our builder and are going to be taken care of before the house goes to drywall next week.

Insulation appeared in our house Saturday. Here is the garage.

Living room with a stack of drywall and all the walls insulated.

Jan standing in the kitchen.